Project

Preci-Spark

We successfully delivered a turnkey solar PV installation under a Power Purchase Agreement (PPA), managing the full commercial and contractual process. Beyond this we also designed, constructed, and commissioned this asset, installing a Fall Protection System. 

Additionally, we completed a large amount of roof cut edge corrosion treatment and encapsulated roof fixings to assist the tenant in meeting their FRI lease obligations. 

Challenges

The challenge was to optimise the solar PV system size for maximum electricity generation, savings, and CO2 reduction. 

To complete the roof cut edge corrosion treatment works during the winter months when weather conditions were against us completing the works and obtaining the manufacturer warranties.

Limited capacity of the Main LV Distribution Board resulting in two points of connection.

Scope

  • PPA commercial negotiation and contract execution
  • Grid connection agreement
  • Solar PV design, build and commissioning
  • Roof cut edge corrosion treatment
  • Roof fixing encapsulation
  • Fall protection system design and installation
  • 5 year operations and maintenance of the solar PV and annual recertification of fall protection system
  • Solar PV performance guarantee

Innovations

  • Completion of HD Sharman’s Seamsil® 100 Cut-Edge Corrosion treatment and obtaining manufacturer warranties.
  • Installation of galvanised wire mesh sheets over twenty-three skylights.
  • Construction of outdoor covered, palisade fenced, lockable solar compound.

Landlord

Hudson Advisors

Site Location

Coalville

System Size

326.19 kWp dc
240 kW ac

Annual Electricity Output

290 MWh

Annual CO2 Emissions Reduction

65.4 tonnes

Number of Solar Panels

784